PUE 1.6: meter installation, CTs, sealing, insulation monitoring.
| Document | PUE 7, Section 1.6 Metering and insulation monitoring |
| Edition | 2002 (ПУЭ-7, разд. 1.6) |
| Status | Current |
| Issued by | Ministry of Energy of Russia |
| Applies to | Metering, energy accounting and insulation monitoring |
| № | Chapter / section |
|---|---|
| 1.6.1–1.6.5 | General |
| 1.6.6–1.6.18 | Meter installation |
| 1.6.19–1.6.34 | CTs, metering circuits, sealing |
| 1.6.35–1.6.42 | Insulation monitoring |
1.6.6 Meters at the ownership boundary; 1.6.13 direct connection up to 100 A; 1.6.16 height 0.8–1.7 m.
CTs above 100 A; meters and CTs sealed (1.6.26).
Continuous monitoring in IT systems; periodic LV checks ≥ 0.5 MΩ.
Automatic single-line diagrams, PUE/GOST/IEC calculations, specification and PDF — from one model.
Start freeData is for reference. Final design decisions must follow current regulations and a qualified engineer.
← Back to the country: PUE Russia: Rules for Electrical Installations · World electrical installation rules