Procedure

Application to the network owner → technical conditions (TC) → contract → execution → connection and meter sealing. In RF, 550 ₽ for up to 15 kW (standard procedure).

Technical conditions

TC specify: allocated power, connection point, metering requirements, protection. The project is made per the TC.

Documents from the owner

Passport, ownership documents, plan of the land plot. The network organization prepares the contract.

What the electrician does

Prepares the project per the TC, coordinates the input (pole/box), selects the metering panel, supervises the connection.

Timelines

Standard connection — up to 6 months from the contract; 1 year for complex cases (5th category).

How GorkyCAD helps

The input panel with metering per the TC is designed in GorkyCAD — SLD, panel and passport are ready for the network organization.