Cable cross-sections and ampacityCircuit breaker ratingsElectrical schematic symbols (GOST/IEC)IP protection ratingsRCD types and selectionEarthing systems TN-C, TN-S, TN-C-S, TT, ITWire colour codeBreaker selectivityGenerator selection: petrol or dieselATS and backup powerUPS: types and selectionSolar power plants: types and calculation🌍 World rules

What is ATS

ATS (Automatic Transfer Switch) automatically switches the load from the mains to a backup source (second line, generator, UPS) when voltage fails. In Russia — АВР.

Schemes

SchemeTransfer timeApplication
Manual transfer switch1–3 minCountry houses
Contactor ATS0.5–2 sHomes
ATS + generator auto start10–60 sHomes with generators
ATS + online UPS0 msServers, boilers, medical

PUE requirements

Category 1 consumers (PUE 1.2.17) need two independent sources with ATS; the special group (operating theatres, fire pumps) — a third source (1.2.18). Fire-protection devices — category 1 with ATS (7.2.36).

Transfer times

Design with GorkyCAD Pro